4 The table shows the planned time and budget for a legal consulting project being developed for a client in Copenhagen, Denmark. Complete an earned value analysis (EVA) for the project, based at the end of month 4, given that only activities A, B and C have been completed and spending to date has been :38,250.

Activity Planned time Planned budget A 1 month :26,000 B 1 month :10,500 C 1 month :6,750 D 1 month :13,000 E 1 month :9,650 F 1 month :12,750 G 1 month :8,750 TOTAL 7 months @87,400