5. In the forward scheduling approach, which statement is true: (a) The scheduler begins with a planned

Question:

5. In the forward scheduling approach, which statement is true:

(a) The scheduler begins with a planned receipt date and moves backward in time

(b) Start with due date and work backward through operations reviewing lead times

(c) Less WIP but must have accurate lead time

(d) Jobs are given earliest available time slot in operation