5. Which statement is correct for the rules to determine batch size in Optimized Production Technology (OPT)?

Question:

5. Which statement is correct for the rules to determine batch size in Optimized Production Technology (OPT)?

(a) The use of a non-bottleneck resource should be determined

(b) Activating a resource is not necessarily the same as utilizing a resource

(c) The process batch size should not be fixed

(d) Time lost at a bottleneck is the loss for the whole system.