6 A production process is required to produce 980 of product X, 560 of product Y and...

Question:

6 A production process is required to produce 980 of product X, 560 of product Y and 280 of product Z in a 4-week period. If the process works 7 hours per day and 5 days per week, devise a production schedule per hour that would meet this demand. (Tip: refer to the section on Levelling product or service schedules (Heijunka).)