a) Draw a precedence diagram of this operation b) Given the demand, what is the cycle time
Question:
a) Draw a precedence diagram of this operation
b) Given the demand, what is the cycle time for this operation?
c) What is the theoretical minimum number of workstations?
d) Assign tasks to workstations.
e) What is the overall actual efficiency of the assembly line?
• • 9.26 Given the following task, times, and sequence, develop a balanced line capable of operating with a 10-minute cycle time at Dave Visser’s company.
a) Draw the precedence diagram.
b) Assign tasks to the minimum feasible number of workstations according to the greatest time remaining (ranked positional weight) decision rule.
c) What is the efficiency of the process?
Step by Step Answer: