A specialised assembly unit is supposed to be experiencing a 90% learning curve. If the 50th assembled

Question:

A specialised assembly unit is supposed to be experiencing a 90% learning curve. If the 50th assembled unit required a total of 3 hours of labour, what would be the time required for the 5th, 25th, 100th, 200th and 500th unit?