Boeing completed production on its forty-fifth 787 airliner at a cost of $184 million. The first plane

Question:

Boeing completed production on its forty-fifth 787 airliner at a cost of $184 million. The first plane off the assembly line cost $448 million. What is Boeing’s learning-curve rate for this model?

APPROACH c We use Equation (E-3), with costs for T1 and T45 known, and then find the learningcurve coefficient (C) in Table E.3