Consider the details of a project as shown below: (a) Construct the CPM network. (b) Determine the
Question:
Consider the details of a project as shown below:
(a) Construct the CPM network.
(b) Determine the critical path.
(c) Compute total floats and free floats for non-critical activities.
Immediate Duration Activity Predecessor(s) (Months)
A — 4 B — 8 C — 5 D A 4 E A 5 F B 7 G B 4 H C 8 I C 3 J D 6 K E 5 L F 4 M G 12 N H 7 O I 10 P J,L 5 Q M,N,0 8 AppendixLO1