Consider the following data summarizing the details of a project involving 14 activities. Project Details Immediate Duration
Question:
Consider the following data summarizing the details of a project involving 14 activities.
Project Details Immediate Duration Activity Predecessor(s) (Months)
A — 2 B — 6 C — 4 D B 3 E A 6 F A 8 G B 3 H C,D 7 I C 2 J E 5 K F,G,H 4 L F,G,H 3 M I 13 N K 7
(a) Construct the CPM network.
(b) Determine the critical path.
(c) Compute total floats and free floats for non-critical activities.