Consider the following problem in single machine scheduling with independent jobs. Job j 1 2 3
Question:
Consider the following problem in single machine scheduling with independent jobs.
Job — j 1 2 3 4 5 5 12 8 10 3 10 16 11 16 6 Find the optimal sequence which minimizes the mean tardiness.