Consider the following project: Activity Immediate predecessor/s A B C A D A, B E

Question:

Consider the following project:

Activity Immediate predecessor/s A –

B –

C A D A, B E B, C F D, E For the above project, the following arrow diagram is drawn:
Is there any flaw in the above diagram? If so, draw an improved arrow diagram.

Step by Step Answer: