Consider the following project: Activity Immediate predecessor/s A B C A D A, B E
Question:
Consider the following project:
Activity Immediate predecessor/s A –
B –
C A D A, B E B, C F D, E For the above project, the following arrow diagram is drawn:
Is there any flaw in the above diagram? If so, draw an improved arrow diagram.
Step by Step Answer: