Consider the following single machine scheduling problem. Job j 1 2 3 4 5 Processing time (t1)
Question:
Consider the following single machine scheduling problem.
Job —j 1 2 3 4 5 Processing time (t1) (hrs) 20 8 7 10 9 Find the optimal sequence which will minimize the mean flow time and also obtain the minimum mean flow time.