Consider the following single machine scheduling problem with weights. Job j 1 2 3 4 5 Processing

Question:

Consider the following single machine scheduling problem with weights.

Job —j 1 2 3 4 5 Processing time (t1) 15 4 5 14 8 Weight (w1) 1 2 1 2 3 Determine the sequence which will minimize the weighted mean flow time of the above problem.

Also find the weighted mean flow time.