Find the makespan using the CDS heuristic for the following flow shop problem: Job j tfi tj2

Question:

Find the makespan using the CDS heuristic for the following flow shop problem:

Job j tfi tj2 ti3 tj4 1 5 4 8 9 2 4 8 3 6 3 2 3 5 8 4 4 5 4 3.