First Printing in Winter Park, Florida, wants to use a Gantt chart to show the scheduling of

Question:

First Printing in Winter Park, Florida, wants to use a Gantt chart to show the scheduling of three orders, jobs A, B, and C.

APPROACH c In Figure 15.4, each pair of brackets on the time axis denotes the estimated starting and finishing of a job enclosed within it. The solid bars reflect the actual status or progress of the job.

We are just finishing day 5