Given the following Activity Immediate predecessor Duration, in days A 9 B 20 C 10 DA 11
Question:
Given the following Activity Immediate predecessor Duration, in days A– 9 B– 20 C– 10 DA 11 EC 10 F B, C 4 GF 2 H D, F 5 I E, F, K18 J G, H14 K– 24 LK 6
(a) Draw the CPM diagram.
(b) Find out the critical activities.
(c) Compute the total, free and independent floats for activities E, D, G, H and L.
Step by Step Answer: