In , in the process of limiting the peak manpower requirement to the given constraint on the

Question:

In , in the process of limiting the peak manpower requirement to the given constraint on the manpower availability, the project completion time may be extended beyond the original completion time.

(a) Resource allocation

(b) PERT

(c) Network crashing

(d) Resource levelling AppendixLO1