In LOB, at a process stage, there will be under production if the tip of the vertical

Question:

In LOB, at a process stage, there will be under production if the tip of the vertical strip of that process stage is the horizontal line drawn with respect to the given review date from the cumulative delivery schedule graph.

(a) Above

(b) Below

(c) Touching

(d) None of the above AppendixLO1