In LOB, at a process stage, there will be under production if the tip of the vertical
Question:
In LOB, at a process stage, there will be under production if the tip of the vertical strip of that process stage is the horizontal line drawn with respect to the given review date from the cumulative delivery schedule graph.
(a) Above
(b) Below
(c) Touching
(d) None of the above AppendixLO1
Step by Step Answer: