In network crashing, if more than one critical path exists, then for further crashing, one activity from
Question:
In network crashing, if more than one critical path exists, then for further crashing, one activity from each critical path to be selected with the cost slope.
(a) Maximum
(b) Minimum
(c) Average
(d) None of the above AppendixLO1