In path, an activity may be preponed or postponed. (a) Normal (b) Non-critical (c) Critical (d) None
Question:
In path, an activity may be preponed or postponed.
(a) Normal
(b) Non-critical
(c) Critical
(d) None of the above AppendixLO1