In , probabilistic aspect of time duration of the activities are considered. (a) CPM (b) PERT (c)
Question:
In , probabilistic aspect of time duration of the activities are considered.
(a) CPM
(b) PERT
(c) CERT
(d) XERT AppendixLO1