In the algorithm to minimize the mean flow time of the single machine scheduling problem with parallel
Question:
In the algorithm to minimize the mean flow time of the single machine scheduling problem with parallel processors, the first step uses rule to form ordered job list.
(a) LPT
(b) EDD
(c) SPT
(d) None of the above AppendixLO1