In the branch and bound method applied to minimize the total tardiness of the single machine scheduling

Question:

In the branch and bound method applied to minimize the total tardiness of the single machine scheduling problem, the sequence is constructed from the of the sequence.

(a) Beginning

(b) Middle

(c) End

(d) None of the above AppendixLO1