In the branch and bound method applied to minimize the total tardiness of the single machine scheduling

Question:

In the branch and bound method applied to minimize the total tardiness of the single machine scheduling problem, as per dominance property, the condition to be satisfied for at least one unassigned job is

(a) di < q,

(b) qa

(c) di > qa

(d) None of the above AppendixLO1