In the job shop scheduling with 2 machines and n jobs, in the Gantt chart to minimize
Question:
In the job shop scheduling with 2 machines and n jobs, in the Gantt chart to minimize the makespan, a line is drawn from the origin to the upper corner by avoiding the regions.
(a) Left
(b) Right
(c) Both
(a) and
(b)
(d) None of the above AppendixLO1