In the job shop scheduling with 2 machines and n jobs, in the Gantt chart to minimize
Question:
In the job shop scheduling with 2 machines and n jobs, in the Gantt chart to minimize the makespan, a line with slope is drawn from the origin to the upper right corner by avoiding the regions.
(a) 15°
(b) 30°
(c) 45°
(d) 60°