In the notation of a sub-problem P of the branch and bound method applied to minimizing the

Question:

In the notation of a sub-problem P of the branch and bound method applied to minimizing the total tardiness in the single machine scheduling problem, represents the jobs.

(a) The full sequence

(b) A partial sequence

(c) Compliment of a partial sequence

(d) None of the above.