is product-wise scheduling. (a) Aggregate planning (b) Master production scheduling (c) Both (a) and (b) (d) None
Question:
is product-wise scheduling.
(a) Aggregate planning
(b) Master production scheduling
(c) Both
(a) and
(b)
(d) None of the above 15 Master production scheduling gives top level input to
(a) Assembly line balancing
(b) Layout design
(c) MRP
(d) None of the above AppendixLO1