Kevin Watson, the production planner at Wiz Products, needs to develop a capacity plan for a work
Question:
Kevin Watson, the production planner at Wiz Products, needs to develop a capacity plan for a work center. He has the production orders shown below for the next 5 days. There are 12 hours available in the work cell each day. The parts being produced require 1 hour each
APPROACH c Compute the time available in the work center and the time necessary to complete the production requirements
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management: Sustainability And Supply Chain Management
ISBN: 9780135225899,9780135202722
13th Edition
Authors: Jay Heizer; Barry Render; Chuck Munson