Kevin Watson, the production planner at Wiz Products, needs to develop a capacity plan for a work

Question:

Kevin Watson, the production planner at Wiz Products, needs to develop a capacity plan for a work center. He has the production orders shown below for the next 5 days. There are 12 hours available in the work cell each day. The parts being produced require 1 hour each

image text in transcribed

APPROACH c Compute the time available in the work center and the time necessary to complete the production requirements