Milwaukee Papers managers now wish to know the projects variance and standard deviation. APPROACH c Because the
Question:
Milwaukee Paper’s managers now wish to know the project’s variance and standard deviation.
APPROACH c Because the activities are independent, we can add the variances of the activities on the critical path and then take the square root to determine the project’s standard deviation