Show Milwaukee Papers critical path and find the project completion time. APPROACH c We use Table 3.3

Question:

Show Milwaukee Paper’s critical path and find the project completion time.

APPROACH c We use Table 3.3 and Overlay 3 of Figure 3.10. Overlay 3 of Figure 3.10 indicates that the total project completion time of 15 weeks corresponds to the longest path in the network. That path is Start-A-C-E-G-H in network form. It is shown with thick blue arrows.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: