The activities involved in Alpha Garment Manufacturing Company are listed below with their time estimates. Draw the
Question:
The activities involved in Alpha Garment Manufacturing Company are listed below with their time estimates. Draw the network for the given activities and carry out the critical path calculations.
Description Duration Activity Predecessor(s) Immediate (Days)
A Forecast sales volume — 10 B Study competitive market — 7 C Design item and facilities A 5 D Prepare production plan C 3 E Estimate cost of production D 2 F Set sales price B,E 1 G Prepare budget F 14 AppendixLO1
Step by Step Answer: