The company aims to produce 60 units of the product per day. Group the activities into work
Question:
The company aims to produce 60 units of the product per day.
Group the activities into work stations using Rank Positional Weight Method and compute Balancing Efficiency.
Operation Number Immediate Preceding Tasks Duration (Min)
1 — 8 2 1 12 3 1 15 4 2 10 5 2 14 6 2 9 7 3 11 8 3 16 9 3 20 10 4, 5 8 11 6, 7 13 12 7, 8, 9 17 13 10, 11 6 14 11, 12 5 15 13, 14 12.AppendixLO1