The Johnson's rule can be extended to 3 machines and n jobs flow shop scheduling problem, if
Question:
The Johnson's rule can be extended to 3 machines and n jobs flow shop scheduling problem, if one of the following conditions is satisfied:
(a) minimum processing time on machine 1 is more than the minimum processing time on machine 2 or maximum processing time on machine 3 is more than the minimum processing time on machine 2
(b) maximum processing time on machine 1 is more than the minimum processing time on machine 2 or maximum processing time on machine 3 is more than the maximum processing time on machine 2
(c) maximum processing time on machine 1 is more than the minimum processing time on machine 2 or maximum processing time on machine 3 is more than the minimum processing time on machine 2
(d) None of the above AppendixLO1