Question: You are a new project manager working in the PMO. Your project customer is the Finance department. The Finance department is uncooperative when working with
You are a new project manager working in the PMO. Your project customer is the Finance department. The Finance department is uncooperative when working with the PMO. You have experienced some pushback from members of the finance team on following established project management processes, and they repeatedly go around you to team members and other stakeholders with project information. What factor of influence on communication does this represent?
A. Cultural differences B. Personal preferences C. Interorganizational differences D. Intraorganizational differences