Question: You are a project manager for a telecommunications company assigned to a project to deploy a new wireless network using a technology that does not
You are a project manager for a telecommunications company assigned to a project to deploy a new wireless network using a technology that does not have a proven track record. One of the key stakeholders introduces a change that could impact the schedule. Which of the following does this describe?
A. Communication method B. Factor influencing communication C. Communication trigger D. Communication preferences