172 You have been asked to use the expected-value model to assess the risk in developing a...
Question:
17–2 You have been asked to use the expected-value model to assess the risk in developing a new product. Each strategy requires a different sum of money to be invested and produces a different profit payoff as shown below:
8. A More Constructive Test Approach Is Key to Better Weapon System Outcomes, Best Practice Series, GAO/NSIAD-00-199, Government Accounting Office, July 2000, pp. 23–25.
Assume that the probabilities for each state are 30 percent, 50 percent, and 20 percent, respectively.
a. Using the concept of expected value, what risk (i.e., strategy) should be taken?
b. If the project manager adopts a go-for-broke attitude, what strategy should be selected?
c. If the project manager is a pessimist and does not have the option of strategy S5, what risk would be taken?
d. Would your answer to part c change if strategy S5 were an option?
Step by Step Answer:
Project Management A Systems Approach To Planning Scheduling And Controlling
ISBN: 9780471225775
8th Edition
Authors: Harold R. Kerzner