Question: 5 Because of resource constraints, Activity G cannot begin until January 23. G had 3 days slack and is loaded five days late, finishing on

5 Because of resource constraints, Activity G cannot begin until January 23. G had 3 days slack and is loaded five days late, finishing on January 26. Total delay for Activity G is 2 days.