A project scheduler can help the project manager identify resource over allocation. What is the best example
Question:
A project scheduler can help the project manager identify resource over allocation. What is the best example of resource over allocation?
A. Too many project team members on one task B. Too many project team members on the project C. An individual with too much work in the project timeline D. An individual assigned more than 40 hours in a week
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: