A project to develop technology training seminars is 5 days behind schedule at day 65. It had

Question:

A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000.

Estimate the schedule and cost variances. Re-estimate the variances if the actual cost had been $750,000.

LO1

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management A Strategic Managerial Approach

ISBN: 9781119369097

10th Edition

Authors: Jack R. Meredith, Scott M. Shafer, Samuel J. Mantel Jr.

Question Posted: