A project to develop technology training seminars is 5 days behind schedule at day 65. It had
Question:
A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000.
Estimate the schedule and cost variances. Re-estimate the variances if the actual cost had been $750,000.