Given an activity in an advertising project whose planned cost was $12,000 but actual cost to date
Question:
Given an activity in an advertising project whose planned cost was $12,000 but actual cost to date is $10,000 so far and the value completed is only 70 percent, calculate the cost and schedule variances. Will the client be pleased or angry?LO1
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management A Strategic Managerial Approach
ISBN: 9781119369097
10th Edition
Authors: Jack R. Meredith, Scott M. Shafer, Samuel J. Mantel Jr.
Question Posted: