Question: a. What costs are associated with accelerating other project activities? It may be that activity Xs unit cost of $10,000 per week is a genuine
a. What costs are associated with accelerating other project activities? It may be that activity X’s unit cost of $10,000 per week is a genuine bargain. Suppose, for example, that an alternative activity would cost the project $25,000 for each week’s acceleration.