Activity A is worth $100, is complete, and actually cost $150. Activity B is worth $500, is

Question:

Activity A is worth $100, is complete, and actually cost

$150. Activity B is worth $500, is 75% complete, and has actually cost $400 so far. Activity C is worth $500, is 25%

complete, and has actually cost $200 so far. What is the estimated cost to completion for the project?

a. $1,100

b. $750

c. $880

d. $1,375