An Internet project is about 65 percent complete and has had its challenges. As of the last

Question:

An Internet project is about 65 percent complete and has had its challenges. As of the last status report, it appears to be on track regarding cost, schedule, and scope. Senior management tells you that the sponsor has some serious concerns about the project. You don’t understand why, based on the last status report. What would be the best thing to do first?

a. Evaluate the schedule and budget to verify the triple constraint health of the project.

b. Ignore senior management, as the project is in good shape.

c. Tell senior management that the project is in good shape.

d. Meet with the sponsor and find out what the sponsor’s concerns are.