Assume that you are a project manager in a software firm and have been asked to calculate
Question:
Assume that you are a project manager in a software firm and have been asked to calculate the expected cost for a new fast-food epos system. Referring to historical information, you know that the developers can handle 8 function points each person-month and that the cost per developer in your company is $5,000 per month. The project for which the costs you are estimating is based on the following requirements:
Additionally, you know that the complexity weighting for these functions follows a standard internal formula, shown as:
a. Calculate the total number of function points for the project.
b. Calculate the total expected cost of the project.