Assume that you have completed three months of the project. The BAC was $120,000 for this six-month
Question:
Assume that you have completed three months of the project. The BAC was $120,000 for this six-month project. You can also make the following assumptions:
PV = $60,000
EV = $55,000
AC = $50,000
a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: