Calculate the fully loaded cost of labor for Sally, your project assistant, using the following data: Hourly

Question:

Calculate the fully loaded cost of labor for Sally, your project assistant, using the following data:

Hourly rate: $25/hr Hours needed: 260 Overhead rate: 65%