Consider the following network for conducting a 2-week (10 working days) computer training class: a. Construct a

Question:

Consider the following network for conducting a 2-week

(10 working days) computer training class:

image text in transcribed

a. Construct a schedule showing:
ESs for all activities LSs for all activities Slacks for all activities Critical path

b. Given the following

image text in transcribed

1. Find the crash cost per day.
2. Which activities should be crashed to meet a project deadline of 10 days with a minimum cost? Assume partial crashing.
3. Find the new cost.