Is partial crashing an appropriate assumption in this kind of project? 4. Given the following highway rerouting

Question:

Is partial crashing an appropriate assumption in this kind of project?

4. Given the following highway rerouting project,

image text in transcribed

a. Draw the network.

b. Find the ESs, LSs, and slacks.

c. Find the critical path.

d. If the project has a 1 1/2-year deadline for reopening, should we consider crashing some activities? Explain.