The following data were obtained from a study of the times required to conduct a consumer test

Question:

The following data were obtained from a study of the times required to conduct a consumer test panel study:

image text in transcribed

a. Find the all-normal schedule and cost.

b. Find the all-crash schedule and cost.

c. Find the total cost required to expedite all activities from all-normal (case

a) to all-crash (case b).

d. Find the least-cost plan for the all-crash problem (b).
Assume partial crashing.